04/02/05

REVIEWED PLANNED STAGES:

  • 09/02/05 Place order for electronics
  • 16/02/05 Presentation of artwork to client in York
  • 15-18/02/05 Final glass lamination test before fabrication to confirm kiln setting
  • 23/02/05 Clients approval of artwork by
  • 24/02/05 Final approved artwork sent to Elumin8 with screen separation (Pay Elumin8)
  • 24/02/05 Order glass/ framing job from Fusion Glass (Pay Fusion Glass)
  • 03/03/05 Return of printed EL from Elumin8
  • 03-07/03/05 Full test run of EL prints
  • 07/03/05 Lamps delivered to Fusion glass for lamination and framing
  • 07/03/05 Receive electronics
  • 08-15/03/05 Electronic testing with sensor and serial connection
  • 12/04/05 Completion date for fabrication (from Fusion Glass)
  • 13-22/04/05 Full test run of glass laminated prints, electronic drivers and weather sensors (at Fusion Glass)
  • 25-27/04/05 Transport and onsite installation
  • 28/04/05 Software calibration


-- Main.rachel - 04 Feb 2005
to top


Openloop.YorkArtGalleryPlannedStagesr1.2 - 04 Feb 2005 - 13:26 - HiazHhzz
Contact Loop.pH: Unit 2, 231 Stoke Newington Church Street, London, N16 9HP, UK,
t +44 20 7812 9188, e info(at)loop.ph
Copyright © 2003 - 2009 by Loop.pH Ltd. All material on this website is the property of the contributing authors.